33kV pole dressing on the SOTTA diversion

SOTTA 33kV overhead line diversion

Construction of a 1,007.8m diversion, transfer of supply and removal of the previous line.

June 2025Mining InfrastructureNyanzaga

Project Overview

33kV line diversion at Nyanzaga

KELM constructed a new 33kV overhead line to divert supply away from an existing corridor affected by infrastructure development. The work included route surveying, new line construction, switching coordination and removal of the previous line.

The new route was completed, tested and integrated before the previous poles, conductors and hardware were safely removed.

Client
SOTTA Mining Corporation
Programme
Started and completed June 2025
Location
Nyanzaga, Tanzania
Route Length
1,007.8m of 33kV overhead line
Key Constraint
Transition from the existing route while maintaining supply continuity

What KELM Did

Survey, construction and supply transfer

New Route Design

Surveyed and set out the diversion corridor to clear planned infrastructure works.

Line Construction

Installed poles, insulators, crossarms and conductors with controlled sagging and tensioning.

Supply Transfer

Planned switching and temporary arrangements to manage continuity during cutover.

Demolition & Handover

Removed the old line, restored the site and completed testing and as-built documentation.

Planning a line relocation or network diversion?

KELM can coordinate the new route, cutover and safe removal scope.

Discuss The Scope